Baralaba South project
Project overview
Current stage
Description
- Construction and operation of a greenfield, multi-seam, open-cut coal mine which will occur as a continuation of the existing Baralaba North Mine.
- Open cut coal mine extracting up to 2.5 million tonnes per annum (Mtpa) of run-of-mine (ROM) coal.
- Conventional truck and shovel methods.
- Conventional coal handling and preparation plant and conveyor systems.
- Haul road and ancillary access tracks.
- Water management infrastructure; including multiple mine water dams, sediment dams and clean water dams.
- A realignment of approximately 4.5km of the Moura—Baralaba Road.
- A new power line and associated upgrades to Powerlink’s Baralaba Substation.
- An external supply of water to the mine during extended dry periods from the Dawson Valley Scheme; groundwater bores or; the Benleith Water Scheme.
- Support infrastructure.
Proponent
- Baralaba South Pty Ltd.
Location
- Approximately 115km southwest of Rockhampton and 8km south of Baralaba.
Local government
- Banana Shire Council.
Lifespan
- Approximately 23 years.
Jobs
- Up to 275 (construction).
- Approximately 600 (operational).
Commonwealth approval needed
- Yes (controlled action 2012/6547) single EIS assessment process for Queensland and the Commonwealth.
Environmental Impact Statement (EIS)
The process for the assessment of this project is as follows:
- Submission of draft TOR
- Public notification of draft TOR
- Final TOR issued—EIS in preparation
- Public notification of EIS
- Proponent responds to submissions
- EIS assessment report
The proponent is currently responding to submissions.
The EIS can be viewed online at www.baralabacoal.com.au. Electronic copies can be ordered by phoning Baralaba South Pty Ltd on +61 7 3088 4670 or emailing eis@baralabacoal.com.au.
Notices and documents
Publicly available documents can be obtained by accessing the links below or by contacting Baralaba South Pty Ltd on 07 3088 4670 or emailing eis@baralabacoal.com.au
- s51-52 public notice
- Draft Terms of Reference
- Final Terms of Reference
- s42 Public Notice
- Initial Advice Statement
- s46 Public Notice
Further information
For further information about the EIS process for this proposal, contact the EIS Coordinator (Baralaba South project) on 13QGOV (13 74 68) or email eis@des.qld.gov.au