Cherbourg water quality improvement project

Delivered in partnership by the Australian Government and Queensland Government

Work has begun on the design and construction of water infrastructure upgrades in the Cherbourg community. The water infrastructure upgrades will include:

  • Bert Button Reservoir – a new reservoir, new mains and connections to supply the local area.
  • Town water mains replacement – approximately 2kms of water mains will be replaced throughout the community.
  • Water treatment plant - new raw water pump control system, filtration, dosing systems, UV treatment, associated pipework and modern control systems including SCADA.

The project team will consult with all stakeholders throughout the project. They will work closely with the Cherbourg Aboriginal Shire Council and the local community to consider water safety and reliability issues.

Aspect of projectPhase of ProjectStart date
Stakeholder consultation Mid 2025
Bert Button ReservoirDetailed designJune 2025
 Construction startOctober 2025
 Infrastructure commissioned and operationalEarly 2026
Town water mains replacementDetailed designJune 2025
 Construction startLate 2025
 Infrastructure commissioned and operationalLate 2026
Water treatment plant upgradeDetailed designJuly 2025
 Construction startEarly 2026
 Infrastructure commissioned and operationalLate 2026