Work has begun on the project to design and construct water infrastructure upgrades including:

  • new pre-treatment, improved chemical storage and dosing systems, new clarifiers and filters, UV treatment, associated pipework and pumps, instrumentation and control system known as SCADA to monitor and control the treatment processes.
  • new 2ML treated water reservoir integrated with existing reservoirs storage and connections to provide additional treated water storage.

The project team will consult with all stakeholders throughout the project. They will work closely with Doomadgee Aboriginal Shire Council and the local community to consider water safety and reliability issues.

Phase of projectStart date
Stakeholder consultationJune 2025
New treated water reservoir - finalise design and start constructionJuly 2025
New treated water reservoir - infrastructure commissioned and operationalLate 2025
Water treatment plant upgrades - process reviewLate 2025
Water treatment plant upgrades - detailed designMid 2025
Water treatment plant upgrades - construction startsLate 2025
Water treatment plant upgrades -  infrastructure commissioned and operationalMid 2026